Oak Harbor Clean Water Facility

Industrial and Water Treatment

This phased project replaced two outdated wastewater treatment plants with a modern, LEED Silver-certified facility. Work included coatings and equipment across six buildings, 4,500 SF of fiberglass linings in basins, and 17,000 SF of epoxy coatings in tanks. The team completed 9,737 hours and applied 4,800 gallons of paint with zero safety or quality incidents. The new plant is built to last 50 years.

Challenge

Managing an exceptionally high water table—particularly during winter—resulted in water intrusion into concrete structures, disrupting both the construction schedule and installation sequence

Solution

Applied moisture vapor-retarding coatings to counteract seasonal high water table pressure, enabling construction to proceed while effectively addressing water intrusion along perimeter walls.

Onsite Duration
2 Years
Size
4,500 SF of fiberglass-reinforced secondary containment linings to concrete basins in 3 buildings and 17,000 SF of plural component epoxy coating system to concrete tanks.
General Contractor
Hoffman Construction Company
Designer
MWA, Carollo Engineers
Owner
City of Oak Harbor
Location
Oak Harbor, Washington
Completed
2019
No items found.

The
Team PPC Difference

We deliver lasting quality through decades of expertise and advanced coating solutions. We prioritize your success, ensuring your assets are protected, enhanced, and transformed with precision and a customer-first approach.

PPC delivers lasting quality through decades of expertise and advanced coating solutions.

We prioritize your success, ensuring your assets are protected, enhanced, and transformed with precision and a customer-first approach.

Contact Us